What's New
Follow this
link for news highlights about the STEREO mission. Below, we list
additional entries concerning the STEREO instruments and data.
April 10, 2008
April 10, 2008
The STEREO proposal to the 2008 Senior Review is now available from our
publications
page.
April 8, 2008
The PLASTIC level-1 data archived at the SSC have been moved down into a new
level1 subdirectory to make way
for new level-2 data which are now
available.
March 20, 2008
Daily browse movies are now available from the
CDAW
Data Center. This website allows one to examine side-by-side images from
STEREO Ahead and Behind, or from two SECCHI telescopes on the same spacecraft.
December 27, 2007
Normal operations have resumed on Behind, one day earlier than originally
expected. Both spacecraft are now operating as expected.
December 26, 2007
The Behind star tracker has continued to perform nominally since December
23. Should no further problems develop, Mission Operations plans to resume
normal operations on Friday's track (Dec 28).
December 23, 2007
The Mission Operations team was able today to command the star tracker on
Behind back into operational mode. The star tracker continued to operate
throughout the track. As a precaution, use of the star tracker was suspended
at the end of the track, and the spacecraft was switched from the high gain
to low gain antenna. Mission Operations will continue to staff tracks, and
proceed with caution regarding ST usage. Contingency planning will continue
as will discussion with the star tracker supplier.
December 22, 2007
Problems persist with the star tracker on Behind. The high gain antenna
continues to point to Earth, and the Mission Operations team was able to use
it to download science telemetry. All other spacecraft systems continue to
operate normally.
December 21, 2007
The star tracker on STEREO Behind had an anomaly at 10:10 GMT this morning.
This resulted in the spacecraft autonomously switching to the low gain
antenna. All other spacecraft systems are healthy. Diagnostic telemetry is
being collected, and corrective action is under consideration.
Science data is still being collected, but at the current low telemetry rate
it is not possible to send it to the ground. Some science data may be lost
when the onboard recorders reach their maximum capacity.
December 19, 2007
Running difference images and movies from the SECCHI Heliospheric Imager
HI-2 telescope are now available on the SSC browse and
image search pages. So far, only a few days
are available, mostly in December 2007, but more days will be populated in
the near future.
Unlike the other SECCHI telescopes, the HI-2 images are only processed from
the full resolution level-0 science data. Thus, there is a delay of several
days before any HI-2 images are available.
December 6, 2007
Data from the IMPACT STE detectors are now available on the
SSC archive.
November 29, 2007
August 10, 2007
August 10, 2007
Images from the SECCHI HI1 telescope are now available on the
Daily Browse and Image Search
Tool pages. Because the HI1 images are derived from the level-0 science
data, they take a few days to appear on the website.
August 7, 2007
IMPACT
Level-1 data files are now available.
August 6, 2007
July 10, 2007
June 27, 2007
Several improvements have been made to the in-situ beacon pages at
http://stereo-ssc.nascom.nasa.gov/beacon/beacon_insitu.shtml.
The IMPACT magnetometer data is now in the standard Radial-Tangential-Normal
(RTN) coordinates, and total magnetic field strength has been added to the
plots. New pages have been added for solar energetic particle data.
March 22, 2007
The daily data browse pages are now available at
http://stereo-ssc.nascom.nasa.gov/browse/.
So far, only a few days worth of data are available, but earlier data will be
steadily added. We're also working on adding more in-situ data, as well as the
daily summary plots from SWAVES.
March 21, 2007
February 14, 2007
February 14, 2007
January 23, 2007
The Behind spacecraft flew by the Moon for the second
and last time on January 21. Both spacecraft are now in heading away from
Earth into their orbits around the Sun. The official science mission started
January 22.
The baffle cover on the SECCHI Heliospheric Imager on Behind was opened on
January 11. The scientists were thrilled to find that Comet McNaught was in
the HI-1B field of view. The IMPACT SIT and SEPT covers were opened on Behind
on January 16. All instrument covers are now open.
December 22, 2006:
The A spacecraft performed its lunar flyby last
Friday and is now in heliocentric orbit. The drift rate of the spacecraft is
+21.66 degrees/year (relative to the earth), this is well within its
specification of 22+/- 2 deg/year. The B spacecraft also performed a lunar
flyby, but its trajectory has another flyby scheduled for 21 January 2007. The
B spacecraft successfully completed its final trajectory adjustment maneuver on
this Thursday.
December 14, 2006:
All the subsystems on both spacecraft continue to
perform very well. On Monday, Dec. 11, the Ops team performed a peak power
test on the A-spacecraft. The arrays are producing slightly more power than
expected (720W vs 690W). The G&C team has started to tweak the control
algorithms with the result that mechanical oscillation of the SWAVES antennae
has completely disappeared on both spacecraft. They will continue to fine tune
the system and are planning a test which would run all the wheels through all
speeds to investigate the effect of wheel speed on jitter.
The SECCHI SCIP-B telescope doors (EUVI, COR1 and COR2) were successfully
opened Dec. 13 at 6:30am. First light images were taken and reviewed by a bunch
of very happy scientists on the east and west coasts. Performance was as
expected and comparable to the SCIP-A telescope images taken last week. In
addition, there was a successful opening of the first HI telescope door on
S/C-A. The HI images appear to be exceptional. This means that of the 10
SECCHI telescopes, 8 have successfully opened their doors and taken good
images. The HI-B door, which covers the last 2 telescopes, will open at the end
of December or early January, depending on when we verify that there will be no
more B Observatory maneuvers.
The IMPACT SEPT-NS, SEPT-E and SIT doors were deployed Dec. 14 on Ahead. In
anticipation of this exciting event, the Sun decided to become active making it
easy to confirm the door openings in the science telemetry. There were 5 door
actuations - one for SIT and two for each set of doors on SEPT-E and SEPT-NS.
The door deployments for SIT, SEPT-NS and SEPT-E on Spacecraft B will be in mid
January.
December 4, 2006:
The SECCHI team opened the doors to the SECCHI SCIP-A
instruments and took a few first-light images. Everything went absolutely
smoothly. The three doors opened without incident. The first images look
great even though they were sent down highly compressed to keep the downlink
time reasonable.
The EUVI was opened first and an image from each of the four quadrants looked
fine - no major tears or pinholes in the front filters. The sun is close to
being in the center of the CCD, and the resolution is beautiful.
Then we opened COR2 and took an image--also beautiful, although there is a
slight offpoint (which we expected). The exposure time is just about where we
expected, about 3-4 seconds. We then took a pB sequence of 3 images with the
result that streamers could be seen all the way to the edge of the field.
Then COR1 was opened and it was also as expected. A pB sequence shows the
inner corona nicely out to about 2.5 R, which is what we expected.
November 29, 2006:
Both the Ahead and Behind spacecraft performance
continue to perform very well with all subsystems nominal. The instruments on
both observatories continue to perform well. The SECCHI instrument team is
planning to open the doors on the STEREO-A coronagraphs next week and is
completing internal tests.
The definitive orbit solutions from FDF indicate that the STEREO A Observatory
will achieve its required drift rate without further maneuvers. The STEREO B
Observatory will require a 0.2m/s maneuver currently scheduled approximately
December 8th. Both spacecraft will swingby the moon on December 15th, with a
second lunar swingby for STEREO B on January 21st.
The guide telescope has been enabled on both spacecraft. G&C is assessing the
performance of the attitude control algorithms and will upload new parameters
in December.
November 22, 2006:
The SWAVES team is now producing daily summary plots through their website at
http://swaves.gsfc.nasa.gov.
Follow the links to "data" and then "data plots".
Both the Ahead and Behind spacecraft performance continue to perform very well.
So far, all the planned maneuvers have been completed successfully. The
Mission Operations team is studying the current orbit of the Ahead spacecraft
to see if any more orbital maneuvers are necessary. At least one more delta-V
maneuver is planned for the Behind observatory.
The instruments on both observatories continue to perform well. They were
powered down prior to the P2 maneuvers and then powered back on successfully.
The SEP Central, HET, LET, SIT, SEPT-E, SEPT-NS detectors on IMPACT have been
successfully been powered on and checked out on both observatories. The
Caltech team was able to correlate the first 100 minutes of data from the
STEREO LET instrument on IMPACT with ACE data and the spectra were found to be
consistent.
A spacecraft roll to calibrate the IMPACT Magnetometer was performed on each
observatory. Initial results show that the test was highly successful.
PLASTIC continues to ramp up their high voltage levels on their MCPs. At the
current HV levels they are starting to see counts from penetrating particles or
photons on their position detectors. The SSDs are also seeing penetrating
particles and photons.
The SECCHI team has completed their decontamination heating of the CCDs on the
COR1 and COR2 telescopes and are preparing to do the same with the EUVI and HI
telescopes.
November 14, 2006:
All the spacecraft subsystems are performing very
well. The Guide Telescope was enabled on the A spacecraft Sunday and
acquired the sun. The GT on the B spacecraft was enabled Monday. In both cases
the GT data looks good and the spacecraft algorithms are correctly using the
data. The spacecraft pointing improved markedly with the GT enabled. There
are more planned tests of the GT and spacecraft control algorithms in December
and more tweaking of the control algorithms.
A complete functional test of the both SECCHI suites was completed at the end
of last week and both suites are working well.
The SEP instruments on the B spacecraft were turned on for the first time
this afternoon. Initial indications are very good.
November 6, 2006:
Both spacecraft went through a 25 minute eclipse as
they went through perigee this morning. The spacecraft behaved nominally
throughout eclipse and are now on their way out to moon radius. The Ahead
spacecraft was intentionally sent to Earth Acquisition mode in order to test
the EA system. The operation of the spacecraft was completely nominal in EA
and recovery from EA to Standby was nominal. The instruments on the A
spacecraft were turned off as part of the EA test. The instruments were turned
back on and are continuing with commissioning activities.
The PLASTIC SSD high voltage has been turned on both spacecraft. The MCP high
voltages have been turn on at low voltage on both spacecraft. The MCP voltages
will be ramped up to operational voltages over the next month.
November 3, 2006 UPDATE:
This is STEREO's second week in Earth
orbit(s). It is still in it's first of four phasing orbits--prior to the first
lunar swingby. So far the planned commissioning activities have occurred
without any serious anomalies. The major deployments of solar
arrays, spacecraft separation, and high gain antennas occurred almost
immediately after launch. Since then, the SWAVES antennas on each observatory
have been deployed -- and SWAVES started producing significant science data.
This week, the significant commission events were the execution of the apogee
propulsive maneuvers on both spacecraft that raised their perigees to altitudes
that are comfortably above the atmosphere. These 'burns' were accurate to
within 0.5% -- that is considered very good considering that the observatories
have not yet been fully characterized. The other significant event was the
deployment of the four meter rigid IMPACT boom on each observatory. The MOPS
and Engineering teams performed other important activities: 1) the High Gain
Antennae were successfully exercised over their full range of motion on both
spacecraft. 2) The software team completed its assessment of observed SEU bit
flips on the C&DH and G&C computers and uplinked a patch (after a change
control board review) to correct an issue in the memory scrub software.
Currently, both observatories are operating nominally. All subsystems and
instruments on both observatories have a GREEN health status. Some IMPACT
detectors are currently saturated, possibly due to the proximity to Earth.
This effect is still being investigated. MAG is seeing higher than expected
offsets, which is correctable in software. SWAVES-Behind observes two
interference signals (100 kHz and 16 kHz) associated with the boom deployment.
With the booms deployed the spacecraft pointing has become very stable with the
pointing much less than 7 arc-seconds. We have ended our 24/7 coverage from
DSN and have gone to our nominal 3 hour tracks per day per spacecraft.
November 3, 2006:
Engineering burns were performed on the C thruster set
of both spacecraft. Both burns were completely nominal so all the thrusters
have been checked out and are working. All the spacecraft subsystems are
performing nominally.
November 1, 2006:
Previous item should have reported that PLASTIC was
also partially powered up successfully on both observatories.
The A1 maneuver was successfully completed on both spacecraft.
The two IMPACT booms have been deployed.
The High Gain Antennae were exercised through their full ranges of motion.
October 30, 2006:
Spacecraft subsystems are performing normally. The
SECCHI instrument suites were turned on on both observatories and all telescope
subsystems passed their functional tests. The SWAVES instruments were turned
on, and both sets of antennae were successfully deployed. Parts of the IMPACT
instruments have been powered on.
October 25, 2006:
The twin STEREO observatories were launched at 8:52 p.m. EDT.
[Press release]