Scheduled activities for Week 01:

M Dec 29 (364)  
T Dec 30 (365)  
W Dec 31 (366)  Leap second added at end of day
T Jan 01 (001)  
F Jan 02 (002)  
S Jan 03 (003)  
S Jan 04 (004)  

-------------------------------------------------------------------------------
Scheduled activities for Week 02:

M Jan 05 (005)  
T Jan 06 (006)  
W Jan 07 (007)  HGA calibration, Ahead: 15:30 UT, Behind: 18:00 UT
T Jan 08 (008)  ICAL 1, 14:00 UT
F Jan 09 (009)  
S Jan 10 (010)  COR1 high cadence observations, Ahead: 2-3 UT, Behind: 2-4 UT
S Jan 11 (011)  

-------------------------------------------------------------------------------
Scheduled activities for Week 03:

M Jan 12 (012)  
T Jan 13 (013)  
W Jan 14 (014)  
T Jan 15 (015)  
F Jan 16 (016)  JOP 80, EIT shutterless, 12-15 UT
S Jan 17 (017)  
S Jan 18 (018)  

-------------------------------------------------------------------------------
Scheduled activities for Week 04:

M Jan 19 (019)  
T Jan 20 (020)  
W Jan 21 (021)  Behind: Momentum dump, 19:00 UT
T Jan 22 (022)  Start of extended mission
F Jan 23 (023)  Ahead: SECCHI watchdog reset, 13:29
S Jan 24 (024)  Ahead: SECCHI recovery, 08:00
		STEREO at 90 degrees separation
S Jan 25 (025)  

-------------------------------------------------------------------------------
Scheduled activities for Week 05:

M Jan 26 (026)  
T Jan 27 (027)  
W Jan 28 (028)  
T Jan 29 (029)  
F Jan 30 (030)  
S Jan 31 (031)  
S Feb 01 (032)  

-------------------------------------------------------------------------------
Scheduled activities for Week 06:

M Feb 02 (033)  
T Feb 03 (034)  
W Feb 04 (035)  Ahead: Momentum dump 14:00 UT
T Feb 05 (036)  
F Feb 06 (037)  
S Feb 07 (038)  
S Feb 08 (039)  

-------------------------------------------------------------------------------
Scheduled activities for Week 07:

M Feb 09 (040)  
T Feb 10 (041)  
W Feb 11 (042)  
T Feb 12 (043)  
F Feb 13 (044)  
S Feb 14 (045)  
S Feb 15 (046)  

Notes:
* Feb 12-15		JOP x: High Cadence Study of Quiet Sun Supergranular
			EUV Brightenings.  SECCHI observing 14-18 UT each day

-------------------------------------------------------------------------------
Scheduled activities for Week 08:

M Feb 16 (047)  
T Feb 17 (048)  Behind: SECCHI stepped calibration roll, 13:00
		DAWN - Mars fly-by
W Feb 18 (049)  
T Feb 19 (050)  
F Feb 20 (051)  
S Feb 21 (052)  
S Feb 22 (053)  

-------------------------------------------------------------------------------
Scheduled activities for Week 09:

M Feb 23 (054)  
T Feb 24 (055)  Behind: Power on IMU2
W Feb 25 (056)  
T Feb 26 (057)  Behind: Switch to IMU2, power off IMU1
F Feb 27 (058)  JOP 216: Oscillations in Polar Plumes, SECCHI 12-14 UT
S Feb 28 (059)  JOP 216: Oscillations in Polar Plumes
S Mar 01 (060)  

Notes:

* Target for JOP 216 is south pole

-------------------------------------------------------------------------------
Scheduled activities for Week 10:

M Mar 02 (061)  
T Mar 03 (062)  
W Mar 04 (063)  
T Mar 05 (064)  ICAL1, 13:00 UT
F Mar 06 (065)  Ahead: SECCHI test of extended mission schedule
		Behind: SECCHI watchdog reset 02:28 UT
S Mar 07 (066)  Ahead: SECCHI test of extended mission schedule
S Mar 08 (067)  

-------------------------------------------------------------------------------
Scheduled activities for Week 11:

M Mar 09 (068)  Behind: Momentum dump, 20 UT
T Mar 10 (069)  Ahead: SECCHI stepped calibration roll, 01:20 UT
		Ahead: SECCHI watchdog reset, 8:36 UT
W Mar 11 (070)  Ahead: SECCHI recovery from watchdog reset, 12:56 UT
T Mar 12 (071)  Ahead: SECCHI HI 180 degree roll, 05:30 UT
F Mar 13 (072)  
S Mar 14 (073)  
S Mar 15 (074)  

-------------------------------------------------------------------------------
Scheduled activities for Week 12:

M Mar 16 (075)  
T Mar 17 (076)  Behind: data gap from 4-24 UT due to commanding error
W Mar 18 (077)  Behind: SECCHI HI 180 degree roll, 15:50 UT
T Mar 19 (078)  
F Mar 20 (079)  
S Mar 21 (080)  
S Mar 22 (081)  

-------------------------------------------------------------------------------
Scheduled activities for Week 13:

M Mar 23 (082)  
T Mar 24 (083)  
W Mar 25 (084)  Ahead: momentum dump, 14:30 UT
T Mar 26 (085)  
F Mar 27 (086)  
S Mar 28 (087)  
S Mar 29 (088)  

-------------------------------------------------------------------------------
Scheduled activities for Week 14:

M Mar 30 (089)  
T Mar 31 (090)  
W Apr 01 (091)  JOP 216, Oscillations in Polar Plumes, 12-14 UT
		JOP 80, EIT shutterless, 16-19 UT
T Apr 02 (092)  
F Apr 03 (093)  
S Apr 04 (094)  
S Apr 05 (095)  

Notes:

* JOP 216, Multi-wavelength Observations of Oscillations in Polar Plumes
  Target is south pole/southern coronal hole

-------------------------------------------------------------------------------
Scheduled activities for Week 15:

M Apr 06 (096)  
T Apr 07 (097)  Behind: SECCHI stepped calibration roll, 01:40 UT
W Apr 08 (098)  Both: SECCHI HI 180 degree rolls, Ahead: 03:50, Behind: 07:50
T Apr 09 (099)  ICAL 1, 16:00 UT
F Apr 10 (100)  
S Apr 11 (101)  
S Apr 12 (102)  

-------------------------------------------------------------------------------
Scheduled activities for Week 16:

M Apr 13 (103)  
T Apr 14 (104)  
W Apr 15 (105)  Start of SUMER campaign
		Behind: Switch back to IMU #1
T Apr 16 (106)  
F Apr 17 (107)  
S Apr 18 (108)  
S Apr 19 (109)  

Notes:
* Apr 15-29	SUMER campaign, JOPS 178,195,207,210,214,215,217,218,219
	http://www.mps.mpg.de/services/campaignplanner/planning/campaign-200904/
	Contact Davina Innes-Markiewicz for access

-------------------------------------------------------------------------------
Scheduled activities for Week 17:

M Apr 20 (110)  SUMER campaign continues
T Apr 21 (111)  
W Apr 22 (112)  Behind: Momentum dump, 3 UT
T Apr 23 (113)  
F Apr 24 (114)  
S Apr 25 (115)  
S Apr 26 (116)  

Notes:
* Apr 15-29	SUMER campaign, JOPS 178,195,207,210,214,215,217,218,219
	http://www.mps.mpg.de/services/campaignplanner/planning/campaign-200904/
	Contact Davina Innes-Markiewicz for access

-------------------------------------------------------------------------------
Scheduled activities for Week 18:

M Apr 27 (117)  
T Apr 28 (118)  Ahead:  SECCHI/HI 180 degree roll, 19:50 UT
W Apr 29 (119)  SUMER campaign ends
T Apr 30 (120)  
F May 01 (121)  
S May 02 (122)  
S May 03 (123)  

Notes:
* Apr 15-29	SUMER campaign, JOPS 178,195,207,210,214,215,217,218,219
	http://www.mps.mpg.de/services/campaignplanner/planning/campaign-200904/
	Contact Davina Innes-Markiewicz for access

-------------------------------------------------------------------------------
Scheduled activities for Week 19:

M May 04 (124)  
T May 05 (125)  Ahead: SECCHI watchdog reset, 5:30 UT
W May 06 (126)  Ahead: SECCHI observations resume, 8 UT
		Behind: SECCHI/HI 180 degree roll, 17:50 UT
T May 07 (127)  
F May 08 (128)  
S May 09 (129)  
S May 10 (130)  

-------------------------------------------------------------------------------
Scheduled activities for Week 20:

M May 11 (131)  
T May 12 (132)  Ahead:  Momentum dump, 13:30 UT
		Behind: Spacecraft reset for G&C update.  Preparations for
		power-down start at 18:30 UT
W May 13 (133)  Behind: Recovery from G&C reset.
T May 14 (134)  
F May 15 (135)  
S May 16 (136)  
S May 17 (137)  

-------------------------------------------------------------------------------
Scheduled activities for Week 21:

M May 18 (138)  
T May 19 (139)  
W May 20 (140)  Ahead: SECCHI watchdog reset, 07:36-22 UT
T May 21 (141)  ICAL-1, 14 UT
F May 22 (142)  
S May 23 (143)  
S May 24 (144)  

-------------------------------------------------------------------------------
Scheduled activities for Week 22:

M May 25 (145)  
T May 26 (146)  
W May 27 (147)  SECCHI HI 180 degree rolls, Ahead: 13:50, Behind: 17:50.
T May 28 (148)  
F May 29 (149)  
S May 30 (150)  
S May 31 (151)  

-------------------------------------------------------------------------------
Scheduled activities for Week 23:

M Jun 01 (152)  
T Jun 02 (153)  
W Jun 03 (154)  
T Jun 04 (155)  Behind: Momentum dump, 15:00 UT
F Jun 05 (156)  
S Jun 06 (157)  
S Jun 07 (158)  

-------------------------------------------------------------------------------
Scheduled activities for Week 24:

M Jun 08 (159)  Sunrise launch, 06:27 UT
T Jun 09 (160)  Ahead: SECCHI stepped calibration roll, 09:50 UT
W Jun 10 (161)  
T Jun 11 (162)  
F Jun 12 (163)  
S Jun 13 (164)  
S Jun 14 (165)  

Notes:

* Sunrise 5-day balloon flight
	http://www.mps.mpg.de/services/sunrise/sot/sot.php
	http://star.mpae.gwdg.de/Sunrise/project/publicat/SPIE_2004.pdf

-------------------------------------------------------------------------------
Scheduled activities for Week 25:

M Jun 15 (166)  
T Jun 16 (167)  Behind: SECCHI stepped calibration roll, 11:30 UT
W Jun 17 (168)  SECCHI HI 180 degree rolls, Ahead: 01:50, Behind: 15:50
T Jun 18 (169)  
F Jun 19 (170)  
S Jun 20 (171)  
S Jun 21 (172)  

-------------------------------------------------------------------------------
Scheduled activities for Week 26:

M Jun 22 (173)  
T Jun 23 (174)  
W Jun 24 (175)  
T Jun 25 (176)  Ahead: Momentum dump, 20:00 UT
		ICAL 1: 12 UT
F Jun 26 (177)  
S Jun 27 (178)  
S Jun 28 (179)  

-------------------------------------------------------------------------------
Scheduled activities for Week 27:

M Jun 29 (180)  
T Jun 30 (181)  
W Jul 01 (182)  Behind: HGA calibration, 17:00 UT
T Jul 02 (183)  Ahead:  HGA calibration, 14:00 UT
		EIT shutterless, 17-20 UT
F Jul 03 (184)  
S Jul 04 (185)  
S Jul 05 (186)  

-------------------------------------------------------------------------------
Scheduled activities for Week 28:

M Jul 06 (187)  
T Jul 07 (188)  
W Jul 08 (189)  HI 180 degree rolls, Ahead: 01:50, Behind 15:50 UT
T Jul 09 (190)  
F Jul 10 (191)  
S Jul 11 (192)  
S Jul 12 (193)  

-------------------------------------------------------------------------------
Scheduled activities for Week 29:

M Jul 13 (194)  
T Jul 14 (195)  
W Jul 15 (196)  
T Jul 16 (197)  
F Jul 17 (198)  
S Jul 18 (199)  
S Jul 19 (200)  

-------------------------------------------------------------------------------
Scheduled activities for Week 30:

M Jul 20 (201)  
T Jul 21 (202)  
W Jul 22 (203)  Total solar eclipse
	http://eclipse.gsfc.nasa.gov/SEmono/TSE2009/TSE2009.html
T Jul 23 (204)  Behind: Momentum dump, 23:45 UT
F Jul 24 (205)  
S Jul 25 (206)  
S Jul 26 (207)  

-------------------------------------------------------------------------------
Scheduled activities for Week 31:

M Jul 27 (208)  
T Jul 28 (209)  Ahead: Momentum dump, 12:30 UT
		ICAL01, 17:00 UT
W Jul 29 (210)  Ahead: SECCHI HI 180 degree roll, 21:50
T Jul 30 (211)  
F Jul 31 (212)  
S Aug 01 (213)  
S Aug 02 (214)  

-------------------------------------------------------------------------------
Scheduled activities for Week 32:

M Aug 03 (215)  
T Aug 04 (216)  Ahead: Spacecraft reset for G&C update
W Aug 05 (217)  Ahead: Spacecraft recovery continues
		Behind: SECCHI HI 180 degree roll, 15:50
T Aug 06 (218)  Behind: SECCHI watchdog reset, 21:34 UT
F Aug 07 (219)  Behind: SECCHI observations resume, 4:30 UT
S Aug 08 (220)  
S Aug 09 (221)  

-------------------------------------------------------------------------------
Scheduled activities for Week 33:

M Aug 10 (222)  Both: Begin 6 hour daily DSN tracks
T Aug 11 (223)  
W Aug 12 (224)  Behind: SECCHI watchdog reset, 6:02 UT
T Aug 13 (225)  Behind: Recovery from watchdog reset, 1:34 UT
		Ahead: SECCHI HI 180 degree roll, 01:50 UT
		Ahead: Test of 360 kbps downlink rate
F Aug 14 (226)  
S Aug 15 (227)  
S Aug 16 (228)  

-------------------------------------------------------------------------------
Scheduled activities for Week 34:

M Aug 17 (229)  Ahead: Switch downlink rate to 360 kbps
		Both: SECCHI/EUVI switch to 195 as prime wavelength
T Aug 18 (230)  
W Aug 19 (231)  
T Aug 20 (232)  ICAL-001, 14:00 UT
		Ahead: SECCHI watchdog reset, 18:01 UT
F Aug 21 (233)  Ahead: SECCHI schedule resumes, 14:00 UT
S Aug 22 (234)  
S Aug 23 (235)  

-------------------------------------------------------------------------------
Scheduled activities for Week 35:

M Aug 24 (236)  
T Aug 25 (237)  
W Aug 26 (238)  Ahead: Momentum dump, 14:00 UT
T Aug 27 (239)  
F Aug 28 (240)  
S Aug 29 (241)  
S Aug 30 (242)  

-------------------------------------------------------------------------------
Scheduled activities for Week 36:

M Aug 31 (243)  Ahead: Some corrupted images
T Sep 01 (244)  
W Sep 02 (245)  
T Sep 03 (246)  
F Sep 04 (247)  
S Sep 05 (248)  
S Sep 06 (249)  

-------------------------------------------------------------------------------
Scheduled activities for Week 37:

M Sep 07 (250)  Labor day
T Sep 08 (251)  Behind: Switch downlink rate to 360 kbps
W Sep 09 (252)  
T Sep 10 (253)  Ahead: SECCHI stepped calibration roll, 12:45 UT
F Sep 11 (254)
S Sep 12 (255)  Ahead at L4 Lagrange point  
S Sep 13 (256)  

-------------------------------------------------------------------------------
Scheduled activities for Week 38:

M Sep 14 (257)  ICAL14, Herschel sounding rocket launch, 17:40 UT
	http://sohowww.nascom.nasa.gov/soc/JOPs/ical014-draft.pdf
T Sep 15 (258)  
W Sep 16 (259)  Behind: Momentum dump, 17:00 UT
T Sep 17 (260)  ICAL 001, 15:00 UT
F Sep 18 (261)  
S Sep 19 (262)  
S Sep 20 (263)  

-------------------------------------------------------------------------------
Scheduled activities for Week 39:

M Sep 21 (264)  Behind: aphelion
T Sep 22 (265)  
W Sep 23 (266)  
T Sep 24 (267)  
F Sep 25 (268)  
S Sep 26 (269)  
S Sep 27 (270)  Start of JOP 224

Notes:
* JOP 224, Solar Tomography with Minimal Solar Rotation, Sep 27-Oct 27

-------------------------------------------------------------------------------
Scheduled activities for Week 40:

M Sep 28 (271)  Ahead:  SECCHI watchdog reset, 17:29 UT
T Sep 29 (272)  Messenger - Mercury fly-by
		Ahead:  SECCHI observations resume, 14:00 UT
W Sep 30 (273)  Behind: SECCHI stepped calibration, 18:10 UT
T Oct 01 (274)  
F Oct 02 (275)  
S Oct 03 (276)  
S Oct 04 (277)  

Notes:
* JOP 224, Solar Tomography with Minimal Solar Rotation, Sep 27-Oct 27

-------------------------------------------------------------------------------
Scheduled activities for Week 41:

M Oct 05 (278)  
T Oct 06 (279)  
W Oct 07 (280)  
T Oct 08 (281)  EIT shutterless (TBC)
F Oct 09 (282)  
S Oct 10 (283)  
S Oct 11 (284)  

Notes:
* JOP 224, Solar Tomography with Minimal Solar Rotation, Sep 27-Oct 27

-------------------------------------------------------------------------------
Scheduled activities for Week 42:

M Oct 12 (285)
T Oct 13 (286)
W Oct 14 (287)
T Oct 15 (288)  Ahead: 25th momentum dump, 17:00 UT
F Oct 16 (289)
S Oct 17 (290)
S Oct 18 (291)

Notes:
* JOP 224, Solar Tomography with Minimal Solar Rotation, Sep 27-Oct 27

-------------------------------------------------------------------------------
Scheduled activities for Week 43:

M Oct 19 (292)	Behind: SECCHI watchdog reset and recovery, 05:32-14:51 UT
T Oct 20 (293)
W Oct 21 (294)
T Oct 22 (295)
F Oct 23 (296)	Ahead:  SECCHI watchdog reset, 20:17 UT
S Oct 24 (297)	Ahead:  SECCHI recovery, 10:40 UT
		Behind: SECCHI watchdog reset and recovery, 03:31-23:30 UT
S Oct 25 (298)

Notes:
* JOP 224, Solar Tomography with Minimal Solar Rotation, Sep 27-Oct 27

-------------------------------------------------------------------------------
Scheduled activities for Week 44:

M Oct 26 (299)  Behind: At L5 Lagrange point
T Oct 27 (300)
W Oct 28 (301)
T Oct 29 (302)
F Oct 30 (303)
S Oct 31 (304)
S Nov 01 (305)  Daylight savings ends in U.S., 06:00 UT

Notes:
* JOP 224, Solar Tomography with Minimal Solar Rotation, Sep 27-Oct 27
* JOP 222, Origin of SEPS, Target of opportunity, Oct 28 - Nov 1

-------------------------------------------------------------------------------
Scheduled activities for Week 45:

M Nov 02 (306)  
T Nov 03 (307)  Behind: Momentum dump, 16:00 UT
W Nov 04 (308)  
T Nov 05 (309)  
F Nov 06 (310)  
S Nov 07 (311)  
S Nov 08 (312)  

-------------------------------------------------------------------------------
Scheduled activities for Week 46:

M Nov 09 (313)  
T Nov 10 (314)  
W Nov 11 (315)  
T Nov 12 (316)  
F Nov 13 (317)  
S Nov 14 (318)  
S Nov 15 (319)  Ahead: SECCHI watchdog reset, 16:07 UT

-------------------------------------------------------------------------------
Scheduled activities for Week 47:

M Nov 16 (320)  Ahead: SECCHI recovery, 05:21 UT
T Nov 17 (321)  
W Nov 18 (322)  
T Nov 19 (323)  
F Nov 20 (324)  
S Nov 21 (325)  
S Nov 22 (326)  

-------------------------------------------------------------------------------
Scheduled activities for Week 48:

M Nov 23 (327)  
T Nov 24 (328)  Ahead: SECCHI stepped calibration roll, 14:15
W Nov 25 (329)  
T Nov 26 (330)  Thanksgiving
F Nov 27 (331)  
S Nov 28 (332)  
S Nov 29 (333)  

-------------------------------------------------------------------------------
Scheduled activities for Week 49:

M Nov 30 (334)  Behind: Begin 7 hour daily DSN tracks
T Dec 01 (335)  
W Dec 02 (336)  Ahead: momentum dump, 15:00 UT
T Dec 03 (337)  
F Dec 04 (338)  
S Dec 05 (339)  
S Dec 06 (340)  

-------------------------------------------------------------------------------
Scheduled activities for Week 50:

M Dec 07 (341)  Behind: Switch downlink rate to 240 kbps
T Dec 08 (342)  
W Dec 09 (343)  
T Dec 10 (344)  
F Dec 11 (345)  
S Dec 12 (346)  
S Dec 13 (347)  

-------------------------------------------------------------------------------
Scheduled activities for Week 51:

M Dec 14 (348)  
T Dec 15 (349)  
W Dec 16 (350)  
T Dec 17 (351)  
F Dec 18 (352)  
S Dec 19 (353)  
S Dec 20 (354)  

-------------------------------------------------------------------------------
Scheduled activities for Week 52:

M Dec 21 (355)  
T Dec 22 (356)  Behind: Momentum dump, 16:00 UT
W Dec 23 (357)  
T Dec 24 (358)  
F Dec 25 (359)  Christmas
S Dec 26 (360)  
S Dec 27 (361)  

-------------------------------------------------------------------------------
Scheduled activities for Week 53:

M Dec 28 (362)  
T Dec 29 (363)  
W Dec 30 (364)  
T Dec 31 (365)  
F Jan 01 (001)  New Year
S Jan 02 (002)  
S Jan 03 (003)  

-------------------------------------------------------------------------------

 

Plans last modified Tuesday, 07-Feb-2012 21:28:36 UTC


Last Revised: Tuesday, 20-Jan-2009 20:15:25 UTC
Responsible NASA Official: [email address: Therese.A.Kucera<at>nasa<dot>gov]
Accessibility
Privacy Policy and Important Notices
Feedback and comments: webmaster