Scheduled activities for Week 47:

M Nov 16 (320)  Ahead: SECCHI recovery, 05:21 UT
T Nov 17 (321)  
W Nov 18 (322)  
T Nov 19 (323)  
F Nov 20 (324)  
S Nov 21 (325)  
S Nov 22 (326)  

-------------------------------------------------------------------------------
Scheduled activities for Week 48:

M Nov 23 (327)  
T Nov 24 (328)  Ahead: SECCHI stepped calibration roll, 14:15
W Nov 25 (329)  
T Nov 26 (330)  Thanksgiving
F Nov 27 (331)  
S Nov 28 (332)  
S Nov 29 (333)  

-------------------------------------------------------------------------------
Scheduled activities for Week 49:

M Nov 30 (334)  Behind: Begin 7 hour daily DSN tracks
T Dec 01 (335)  
W Dec 02 (336)  Ahead: momentum dump, 17:30 UT
T Dec 03 (337)  
F Dec 04 (338)  
S Dec 05 (339)  
S Dec 06 (340)  

-------------------------------------------------------------------------------
Scheduled activities for Week 50:

M Dec 07 (341)  Behind: Switch downlink rate to 240 kbps
T Dec 08 (342)  
W Dec 09 (343)  
T Dec 10 (344)  
F Dec 11 (345)  
S Dec 12 (346)  
S Dec 13 (347)  

-------------------------------------------------------------------------------
Scheduled activities for Week 51:

M Dec 14 (348)  
T Dec 15 (349)  
W Dec 16 (350)  
T Dec 17 (351)  
F Dec 18 (352)  
S Dec 19 (353)  
S Dec 20 (354)  

-------------------------------------------------------------------------------

Upcoming events:

2009:

ICAL-001: Dec 14-18

SECCHI Stepped calibration rolls
	Ahead:	Nov 24
	Behind:	Dec 22

* Ongoing		JOP 222, Origin of SEPS, Target of opportunity

2010:

ICAL-001: Jan 11-15, Feb 15-19, Mar 15-19, Apr 12-16, May 3-7

SECCHI Stepped calibration rolls
	Ahead:	Feb 23, May 18, Aug 10, Nov 2
	Behind:	Apr  6, Jul 13, Oct 12

* Jan 6			Both: HGA calibration
* Jan 7,15		EIT shutterless (TBC)
* Spring (TBD)		SUMI sounding rocket launch
	http://adsabs.harvard.edu/abs/2008AGUSMSP51B..01A
* Apr 8,15		EIT shutterless (TBC)
* Apr 19		Ahead: Begin 7 hour daily DSN tracks
* Apr 26		Ahead:  Switch downlink rate to 240 kbps
* Jul 8,15		EIT shutterless (TBC)
* Jul 11		Total solar eclipse
	http://eclipse.gsfc.nasa.gov/SEmono/TSE2010/TSE2010.html
* Jul 14		Both: HGA calibration
* Sep 7			Both: Begin 8 hour daily DSN tracks
* Sep 13		Both: Switch downlink rate to 160 kbps
* Nov 15		Behind: Switch downlink rate to 120 kbps

2011:

* Jan 12		Both: HGA calibration
* Feb 6			STEREO spacecraft at 180 degree separation
* Mar 18		Messenger - Mercury orbital insertion
* Apr 11		Ahead:  Switch downlink rate to 120 kbps
* Jul 13		Both: HGA calibration
* Aug			DAWN - Vesta arrival
* Sep 19		Behind: Switch downlink rate to 96 kbps
* Sep 26		Ahead:  Switch downlink rate to 96 kbps

2012:

* Jan 11		Both: HGA calibration
* May			DAWN - Vesta departure
* Jul 11		Both: HGA calibration
* Aug			Both: Switch downlink rate to 30 kbps
* Nov 13		Total solar eclipse, south Pacific

2013:

* Dec 12		Ahead: Possible Mercury transit (TBC)

2014:

* Apr 29		Behind: Possible Mercury transit (TBC)

2015:

* Feb			DAWN - Ceres arrival
* Jan 10 - Apr 12	Behind: Spacecraft behind Sun
* Feb 17 - Aug 2	Ahead:  Spacecraft behind Sun
* Jul 23 - Nov 10	Behind: Spacecraft behind Sun
* Jul			DAWN - End of nominal mission

 

Plans last modified Monday, 23-Nov-2009 14:33:28 EST